Nathan Road Project
Nathan Road
Client: Hong Kong Mass Transit Railway Corporations
Night work outside Fourseas Building In Jordan
Details
-
Contract No. C2634.01-10E - Relining of the Condensing Water Mains from NIC to JOR (2011 - 2012)
-
Location - Nathan Road
-
1st winter - From Manhole B01 to North Intake Cell (NIC) X 2 nos. of supply and return pipes, From B11 to B13
-
2nd winter - From Manhole B06 to B10 X 2 nos. of supply and return pipes, From B17 to B16
-
Pipe diameter: 600mm
-
Length: Approximately 860m
Job Description
-
Carry out relining works for the condensing water main pipes between Tsim Sha Tsui North Intake Cell and Jordan Station
-
Replace the butterfly valve and install new pipe fittings and other fittings as necessary
-
Drain off the condensing water system and carry out rehabilitation work, closed circuit television (CCTV) inspection and refilling of condensing water mains
CCTV inspection during rehabilitation work.
Road/Traffic arrangement for accessing the manholes.
Achievements
-
Period of contract is scheduled for two years, but actual working days are limited to a certain 3 months in both 1st and 2nd winter
-
A well-planned working schedule, safety plan and risk assessment were fully prepared prior to commencement of work
-
Relining work between B06 and B10 were completed in 5 days during Chinese Lunar Holiday due to contingency reasons
-
Road closure on Nathan Road was required to access the manholes and significant preparation works such as Temporary Traffic Management Scheme (TTM) and Traffic Impact Analysis (TIA), etc., had to be planned and designed in advance
-
Plans were done in the first year in preparation for the application of road closure in the second year
-
Liner had to pass through four 45 degree bends
-
Liner thickness was streamed down to 11mm which further enhances the flow capacity as well as maintaining the quality